A septic tank installation is not simply a matter of excavating a hole and lowering in a tank. In England, a compliant private sewage system starts with checking whether connection to the public foul sewer is reasonably available, assessing the site and discharge route, sizing the system correctly, designing a suitable drainage field, obtaining the necessary approvals and then installing the tank and pipework to the manufacturer's requirements and current standards.

At DGS Limited, we carry out septic tank installations and associated drainage and groundworks across the North East. Our first question is always whether a septic tank is actually the right solution for the site. On some properties a sewage treatment plant or public-sewer connection is more appropriate.

The Installation Process at a Glance

  1. Confirm whether a public foul sewer connection should be used.
  2. Survey the site, ground conditions, levels, access and groundwater constraints.
  3. Calculate the design load and choose a correctly sized system.
  4. Confirm the proposed discharge route and drainage-field suitability.
  5. Obtain planning, building-control or environmental approvals where required.
  6. Excavate and prepare the tank base, drainage trenches and pipe routes.
  7. Install and connect the tank, inlet, outlet, inspection points and drainage field.
  8. Test, commission, backfill and hand over maintenance information to the owner.

Step 1: Check Whether You Should Connect to the Public Foul Sewer

For new discharges started on or after 1 January 2015, the Environment Agency's general binding rules require a public-sewer check. For a single domestic property, you cannot normally rely on the general binding rules for a new private discharge if a public foul sewer is within 30 metres of any boundary of the premises served.

This is important because a septic tank is not intended to be the default choice simply because there is space in the garden. We establish the local sewer position early so the project is designed around the correct drainage strategy.

Private drainage is not a way around an available public sewer

If the general binding rules cannot be met, an environmental permit may be required, and the Environment Agency may expect connection to the public foul sewer where that is a reasonable solution.

Step 2: Establish the Correct Type of Treatment System

A septic tank and a small sewage treatment plant are different. A septic tank settles solids and sends effluent to an infiltration system or drainage field for further treatment in the ground. It must not discharge directly to a river, stream or ditch. A sewage treatment plant provides additional treatment and can, where all rules are met, have different discharge options.

For a qualifying small sewage discharge to ground, the general binding rules set a threshold of up to 2 cubic metres per day. Systems above the threshold, in sensitive locations or unable to meet the rules may need an environmental permit.

Step 3: Carry Out a Proper Site Survey

The survey determines whether the proposed location can physically and legally support the system. We consider the property occupancy, daily wastewater load, available fall, tank access, tanker access for future emptying, groundwater, nearby buildings, watercourses, wells, services, trees, land levels and the area available for a drainage field.

Site access matters from the start. The installation needs safe excavation access, but the finished system also needs practical future access for inspection, maintenance and desludging.

Step 4: Size the System for the Real Wastewater Load

Undersizing a private sewage system is a common route to poor performance. The Environment Agency points installers and operators towards British Water's Flows and Loads guidance when working out treatment capacity. The current British Water code provides a consistent method of calculating sewage load for systems serving up to 1,000 population equivalents.

For a domestic property, occupancy is an important starting point, but extensions, annexes, holiday use, future bedrooms or non-domestic activity can change the design load. We size for the actual intended use rather than simply matching the capacity of the old tank being replaced.

Step 5: Design the Drainage Field, Not Just the Tank

The drainage field is a treatment component in its own right. Environment Agency guidance defines it as a network of perforated pipes laid in trenches so the septic effluent can percolate through the ground for further treatment. A conventional rainwater soakaway is not an acceptable substitute.

Approved Document H gives important siting guidance for drainage fields. It states that a drainage field or mound should be at least 10 metres from a watercourse or permeable drain, at least 50 metres from a point where groundwater is abstracted, and at least 15 metres from a building. Site-specific environmental rules may be more restrictive.

Why Ground Conditions Matter

A drainage field needs soil that can accept and treat the effluent at a suitable rate. If the ground is too impermeable, too freely draining, waterlogged, in a floodplain or constrained by groundwater-protection requirements, a conventional drainage field may be unsuitable. This is why percolation and site assessment come before final layout.

Step 6: Confirm Standards and Approvals

The Environment Agency requires relevant treatment systems to meet the applicable British Standard. Current guidance references BS EN 12566 for septic tanks and small sewage treatment plants and BS 6297:2007 for drainage fields.

For new systems, the operator must also make sure the necessary planning and building-control approvals are in place. Approved Document H is the principal Building Regulations guidance for foul-water drainage and disposal in England.

Where the project falls outside the general binding rules—for example because of volume, location or site constraints—an environmental permit may be needed before the discharge starts.

Step 7: Excavate the Tank and Drainage Routes Safely

Once the design and approvals are in place, excavation can begin. The dig must account for the tank dimensions, manufacturer-specified base, groundwater conditions, lifting requirements, working space and safe trenching. The tank must not be installed on unsuitable or disturbed ground without the support and backfill required by the manufacturer.

Our groundworks service allows us to coordinate excavation, drainage runs, levels and reinstatement as one project.

Step 8: Install the Tank to the Manufacturer's Instructions

Septic tanks are manufactured from different materials and have different anchoring, concrete surround, backfill and groundwater requirements. The installation method must follow the specific product instructions. A tank that is distorted, allowed to float, poorly supported or incorrectly backfilled can fail even if the drainage design itself is sound.

Levels also matter. The inlet, tank and drainage field must work together hydraulically, with inspection and maintenance access remaining available after landscaping.

Step 9: Install the Inlet, Outlet and Inspection Points

The foul drainage from the property is connected to the tank with correct falls and accessible inspection points. The outlet is connected to the approved drainage field, not to a surface-water drain or an improvised soakaway.

Surface water from roofs, driveways and yards should be kept separate from the septic system. Sending stormwater into a septic tank increases hydraulic loading and can overwhelm both the tank and drainage field.

Step 10: Test Before Backfilling

Connections, levels and watertightness should be checked before the installation disappears beneath the ground. Testing at this stage makes defects easier to correct. The system should be commissioned in line with the manufacturer requirements and building-control process.

Step 11: Backfill and Reinstate Carefully

Backfilling is not simply filling the hole with whatever spoil is available. The material and sequence must follow the tank manufacturer's requirements to avoid deformation or damage. Finished ground levels should protect access covers, prevent surface water entering the system and keep the drainage field free from inappropriate structures or vehicle loading.

Step 12: Hand Over a Maintenance Plan

The Environment Agency requires the system to be maintained in good working order. For septic tanks, sludge must be removed before the tank exceeds its maximum capacity and the current guidance says desludging should take place at least once a year or in line with the manufacturer's instructions.

The waste carrier used to remove sludge must be registered. Owners should also keep a simple record of emptying, servicing, repairs and any changes to the system.

What Happens When a Property Is Sold?

The operator selling a property with a private sewage system must give the new operator written information about the system, including its location, drainage arrangement, relevant changes and maintenance requirements. A clear handover record is therefore part of good installation practice, not an afterthought.

Common Septic Installation Mistakes We Avoid

Installation mistakes and why they matter
MistakeWhy it creates problemsBetter approach
Choosing the tank before surveying the siteThe discharge route or ground may be unsuitable.Confirm the drainage strategy and site constraints first.
Undersizing the systemPeak loads can overwhelm treatment and storage capacity.Use current loading guidance and realistic occupancy.
Using a soakaway instead of a drainage fieldA soakaway is designed for rainwater, not septic effluent treatment.Design a compliant infiltration system to BS 6297 principles.
Connecting roof waterStormwater adds unnecessary hydraulic load.Keep foul and surface-water drainage separate.
Discharging a septic tank to a ditch or streamCurrent rules do not allow septic-tank effluent to discharge directly to surface water.Use a compliant drainage field or an appropriate sewage treatment plant solution.
Ignoring future maintenance accessEmptying and repair become difficult or expensive.Plan tanker and inspection access during design.

Percolation Testing and Groundwater Checks

A drainage field only works where the receiving ground can accept effluent at a suitable rate and provide adequate treatment. Site investigation may therefore include trial holes, groundwater observations and percolation testing in accordance with the design approach being used. A single test hole or a test carried out in obviously unrepresentative conditions should not be treated as a complete understanding of the site.

The Environment Agency also restricts qualifying discharges in groundwater source protection zone 1 and near wells, springs or boreholes used for domestic or food-production water. These constraints can rule out an otherwise convenient part of a plot.

What Happens to an Old Septic Tank During Replacement?

Replacement projects need a plan for the existing tank as well as the new one. The old system may need to be emptied, isolated, removed or made safe in accordance with the site design and building-control requirements. Existing inlet drains should be checked before they are reconnected, because there is little value installing a new tank onto cracked, root-damaged or poorly graded pipework.

Where the old drainage field has failed, simply connecting a new tank to the same failed infiltration area will not solve the underlying problem. The receiving ground and new discharge route must be assessed in their own right.

Commissioning Information the Owner Should Keep

After installation, the owner should know where the tank, access covers, inlet, outlet and drainage field are located; what system has been installed; the design capacity; the manufacturer's instructions; the expected maintenance and desludging routine; and any planning, building-control or environmental documentation relevant to the installation.

This information is valuable during future servicing and is also important when the property is sold, because the next operator must receive written information about the private sewage system and how it should be maintained.

How Long Does Installation Take?

There is no reliable universal number. A straightforward replacement with good access and proven ground conditions can progress quickly, while a new system that needs surveys, approvals, drainage-field design, difficult excavation or extensive reinstatement will take longer. We give a project-specific programme once the site and scope are known.

How DGS Limited Manages the Process

We combine private drainage knowledge with excavation and groundworks, which means the tank, connecting pipework, drainage field and reinstatement can be planned as one system. Where the correct solution is not a septic tank, we will explain why and discuss the alternatives.

Learn more about DGS Limited or contact our team to discuss a new or replacement private sewage system.

Planning a Septic Tank Installation?

Start with the site, not the product catalogue. We can help establish the drainage route, ground conditions, loading, excavation requirements and the practical installation sequence before work begins.

Frequently Asked Questions About Septic Tank Installation

Clear answers on site surveys, legal checks, public sewers, drainage fields, tank sizing, excavation, Building Regulations, general binding rules and ongoing maintenance.


No. Current Environment Agency guidance states that a septic tank must discharge to ground through an infiltration system or drainage field. Surface-water discharges require a sewage treatment plant and must meet the relevant rules.

For a new single domestic discharge started on or after 1 January 2015, the general binding rules cannot normally be used if a public foul sewer is within 30 metres of any boundary of the premises served.

The small-sewage-discharge threshold for a qualifying discharge to ground is up to 2 cubic metres per day. Systems outside the rules may need an environmental permit.

Planning requirements depend on the project, but the operator must ensure necessary planning and building-control approvals are in place. These checks should be made before work starts.

New private drainage work is subject to Building Regulations requirements in England. Approved Document H provides the main guidance for foul-water drainage and disposal.

A septic tank mainly settles solids and sends effluent to a drainage field. A sewage treatment plant provides additional treatment and may have different approved discharge options.

The design should reflect the real sewage load and intended occupancy. Environment Agency guidance points to British Water Flows and Loads for sizing treatment systems.

Approved Document H gives guidance that a drainage field or drainage mound should be at least 15 metres from a building, subject to site-specific requirements and other environmental constraints.

Approved Document H gives a minimum of 10 metres from a watercourse or permeable drain, while other environmental rules may impose additional restrictions.

No. A drainage field is a wastewater-treatment infiltration system designed for septic effluent. It is not the same as a rainwater soakaway.

No. Roof and surface water should be kept separate from the foul system because unnecessary stormwater can overload the tank and drainage field.

The Environment Agency says sludge should be removed before maximum capacity is reached and the system should be desludged at least annually or in line with the manufacturer's instructions.

Yes. Inspection, desludging and maintenance access should be considered at design stage so the finished installation remains practical to service.

Environment Agency guidance references relevant BS EN 12566 standards for septic tanks and small sewage treatment plants and BS 6297:2007 for drainage fields.

Yes. We can coordinate excavation, private drainage, tank installation, drainage-field work and reinstatement for suitable projects across the North East.

Sources and References

The factual, regulatory, safety and industry guidance used in this article was checked against the following independent external sources. Sources are listed as plain text and were reviewed on 4th September 2026.

  • Environment Agency / GOV.UK — “General binding rules: small sewage discharge to the ground”, last updated 23 July 2026. Used for current England rules on septic-tank discharge to ground, public foul sewer checks, system standards, maintenance, annual desludging, pollution prevention and transfer of information on sale.
  • Environment Agency / GOV.UK — “General binding rules for small sewage discharges with effect from 2 October 2023”. Used for the 2 cubic metre/day ground threshold, treatment requirements and additional rules for newer discharges.
  • Ministry of Housing, Communities and Local Government — “Drainage and waste disposal: Approved Document H”. Used for Building Regulations context and drainage-field siting guidance including separation from buildings, watercourses and groundwater abstraction points.
  • British Water — “Flows and Loads – Sizing Criteria, Treatment Capacity for Sewage Treatment Systems”. Used for current industry sizing methodology and the importance of declaring all loads when designing non-mains sewage treatment systems.
  • GOV.UK / Environment Agency — “Discharges to surface water and groundwater: environmental permits”. Used for permitting context when a private sewage discharge cannot meet the general binding rules.
  • GOV.UK — Approved Documents collection. Used to confirm the current Approved Document framework for Building Regulations in England.